Published: October 16, 2026 | Category: Critical Minerals – Lithium
PLS Approves P2000 Expansion to Lift Pilgangoora to 2 Mtpa
The Pilgangoora Operation in Western Australia’s Pilbara region, where PLS will build the Jimmagunya processing plant. Photo Credit: PLS
Key Points
- PLS Group (ASX: PLS) took a positive final investment decision on October 16, 2026 for the P2000 Project at its 100%-owned Pilgangoora Operation in Western Australia.
- P2000 adds the Jimmagunya processing plant and lifts spodumene concentrate capacity to about 2.0 million tonnes a year, with first production expected in the September quarter of 2029.
- Project capital is about A$1.9 billion. The feasibility study reports an incremental post-tax NPV of A$2.7 billion and an IRR of 29.5% at a long-term SC6 price assumption of US$1,620 a tonne.
- The updated Pilgangoora Ore Reserve is 249.2 million tonnes at 1.24% Li2O, including a maiden underground reserve, and 10-year average unit operating costs are put at about A$620 a tonne.
- PLS says funding comes from its A$2.3 billion cash balance (as at June 30, 2026) and operating cash flow.
The Investment Decision
PLS Group Limited has approved P2000, the expansion of its Pilgangoora Operation that it has been studying since the 21 June 2024 pre-feasibility study. The completed feasibility study supports about A$1.9 billion of project capital, which includes pre-FID spending approved in June 2026 and excludes separately approved infrastructure work at Pilgangoora.
Pilgangoora sits in Western Australia’s Pilbara region, about 140 km by road from Port Hedland, where PLS exports its spodumene concentrate. PLS has expanded the operation in stages since first production in 2018, and P2000 follows the P680 and P1000 projects.
— Dale Henderson, Managing Director and CEO, PLS“P2000 will transform the scale and competitive position of PLS.”
What Changed From the 2024 Study
The feasibility study moves to a larger plant and a different mining approach. Metallurgical testwork and experience from the ore sorting facility at the Pilgan plant showed that far more contact ore, a blend of ore and host rock from the ore boundary, can be processed without hurting concentrate quality. PLS therefore treats about 67 million tonnes of mineralized contact material, previously classified as waste, as ore.
That change feeds through the plan. Open-pit ore mined rises, the life-of-mine strip ratio falls and the wet plant is sized up by 26%. Capital rises with the larger plant, which PLS attributes to the scale and processing capability of Jimmagunya, scope development and greater project definition.
| Metric | 2024 PFS | 2026 FS |
|---|---|---|
| Open-pit ore mined (Mt) | 211 | 236 |
| Life-of-mine strip ratio | 7.7x | 5.6x |
| Jimmagunya wet plant (Mtpa) | 5.0 | 6.3 |
| 10-year average production (ktpa SC5.2) | 1,895 | 1,970 |
| Unit operating cost, FOB, real (A$/t) | ~600-700 | 620 |
| Project capital (A$ billion) | 1.3 | 1.9 |
PLS adjusted the 2024 cost and capital figures for 9.0% cumulative Perth inflation to make them comparable. As originally stated, the pre-feasibility study showed unit operating costs of A$550-650 a tonne and capital of A$1.2 billion. FOB unit costs exclude freight and royalties and are net of tantalite by-product credits.
Ore Reserve and the Jimmagunya Plant
PLS released an updated Pilgangoora Ore Reserve alongside the decision. Including a maiden underground reserve of 46.5 million tonnes at 1.50% Li2O, the total is 249.2 million tonnes at 1.24% Li2O. PLS says that is a 23% increase in reserve tonnes and a 31% increase in contained lithia against the figures in its FY26 Annual Report. The reference point for the reserve has also moved from run-of-mine to after crushing and ore sorting. The percentage increases therefore compare reserves measured at different points in the process.
Jimmagunya, named by Nyamal elders and meaning “spring country”, will sit next to the existing Pilgan plant. It combines a 9.0 Mtpa dry plant with crushing, ore sorting and covered stockpiling, and a 6.3 Mtpa wet plant with grinding, flotation, tantalum recovery and concentrate dewatering. Average lithia recovery through the wet plant is expected at about 70%, and PLS puts the gain in overall orebody extraction at roughly 17%.
The Ngungaju plant will be idled and kept as flexible capacity. PLS expects P2000 to add about 900,000 pounds a year of contained tantalum pentoxide, as roughly 5% primary tantalite concentrate, on average over the first 10 years.
Contact Ore
Mineralized material at the boundary between the ore body and the host rock. Earlier mine plans classed much of it as waste. Ore sorting and whole-of-ore flotation at Jimmagunya allow PLS to process it, which reduces waste movement and the strip ratio.
Economics, Funding and Schedule
The feasibility study reports an incremental post-tax NPV of A$2.7 billion at an 8% real discount rate and an incremental IRR of 29.5%. Those figures assume a long-term SC6 price of US$1,620 a tonne CIF China, the average of 11 analyst forecasts as at October 12, 2026, and an exchange rate of 0.70 AUD/USD. PLS says a US$250 a tonne rise in that price assumption would add about A$900 million to the NPV.
Capital spending is phased at about A$500 million in FY27, A$900 million in FY28 and A$500 million in FY29. PLS also announced A$600-650 million of enhancing infrastructure at Pilgangoora, covering a road upgrade, a mine services facility and a permanent accommodation village, which sits outside the P2000 figure. PLS says the A$2.7 billion NPV does include an attributable share of that infrastructure spending.
P2000 will be funded from PLS’s cash balance of A$2.3 billion as at June 30, 2026 and operating cash flow, with debt assessed periodically. Construction is highly modularized and PLS does not expect it to disrupt current production. First production is targeted for the September quarter of 2029, with full production after an approximate six-month ramp-up. PLS expects more than 1,000 construction jobs and about 500 permanent roles.
Approvals are not complete. PLS holds the core tenure and primary operating approvals for construction and is progressing the remaining approvals and license amendments needed for the expanded life-of-mine plan.
Sales and the Underground Option
Contracted placement capacity, which reflects recent offtake agreements including PLS’s sole-election rights and Ganfeng extension options, covers about 50% of forecast P2000 volume in FY30. PLS plans to leave the rest unallocated so it can place volume with existing or new customers, and says it continues to receive unsolicited interest in long-term offtake.
PLS also completed a separate underground pre-feasibility study. Combining open-pit and underground ore could support all three Pilgangoora plants at about 2.2 Mtpa on a 10-year average and extend the operating horizon from about 20 years to more than 25. That case is not part of the P2000 decision, capital or economics. A separate underground feasibility study has started, and any underground development needs its own investment decision.
The study figures are forward-looking targets that depend on construction and commissioning. PLS notes that the production targets are underpinned by Ore Reserves of which 6% are proved and 94% probable.