NEWS

Dow and X-energy SMR Project Receives NRC Construction Permit in Texas

Rendering of an X-energy Xe-100 plant, the design permitted for Dow's Seadrift site in Texas

Rendering of the X-energy Xe-100 reactor. Photo Credit: X-energy

Key Points

  • The US Nuclear Regulatory Commission approved a construction permit for four X-energy Xe-100 reactors at Dow’s UCC Seadrift Operations site in Texas, announced November 9, 2026.
  • X-energy says it is the first construction permit for a high-temperature gas-cooled reactor in nearly 60 years, and the first for a pebble-bed design.
  • The permit does not start nuclear construction. Dow expects to consider a preliminary investment decision in 2027 and a final decision before full-scale construction.
  • The four 80 MWe units would supply electricity and high-temperature steam to the Dow site, with first delivery in the early 2030s according to the release.

The Construction Permit

X-energy, Inc. (Nasdaq: XE) and Dow (NYSE: DOW) announced on November 9, 2026 that the Nuclear Regulatory Commission has approved the construction permit application for four Xe-100 small modular reactors at Dow’s UCC Seadrift Operations site in Texas. Dow’s subsidiary Long Mott Energy, LLC submitted the application in March 2025, and the NRC docketed the filing in May 2025 under an 18-month review schedule.

The permit completes the NRC’s safety and environmental reviews for the site. X-energy describes the project as the first advanced nuclear facility approved for an industrial site in the US, and the first high-temperature gas-cooled reactor (HTGR) construction permit in nearly 60 years. It also says this is the first approval of a pebble-bed HTGR. The project is supported by the Department of Energy’s Advanced Reactor Demonstration Program (ARDP).

NRC Chairman Ho Nieh said the agency met its schedule.

“We delivered on the 18-month schedule, proving we can do rigorous safety reviews on predictable timelines that move advanced nuclear technology from design to construction.”

— Ho Nieh, Chairman, US Nuclear Regulatory Commission

The release credits the design’s intrinsic safety, years of pre-application work with the NRC, decades of DOE research on gas-cooled reactors and TRISO fuel, and the ADVANCE Act, which became law in July 2024. X-energy began pre-application engagement with the NRC in 2018, and Dow joined the process in 2023.

Construction Permit

Under the NRC’s 10 CFR Part 50 process, a construction permit authorizes an applicant to build a reactor after the agency reviews the site, the preliminary design and the environmental impacts. Operating the plant requires a separate operating license, which the NRC issues after construction and a further review.

What Happens Next

The permit does not commit Dow to build. The companies say it allows work to advance toward construction readiness: finalizing and standardizing the Xe-100 design, maturing long-lead supply chain items, and developing an operating license application. Dow said it will commit major capital only once design, equipment and materials are in place, which the release says lowers schedule and cost risk.

Edward Stones, Dow’s Business Vice President for Energy and Climate, said the project will be judged on “competitiveness, execution readiness, and capital affordability” before a construction decision. The release says Dow is expected to consider a preliminary investment decision in 2027, and full-scale nuclear construction would start only after a final investment decision.

The release gives the early 2030s as the target for first delivery. The forward-looking statements list the remaining risks: further NRC licensing steps, design changes, Dow’s investment decisions, project financing, supply chain execution and changes to ARDP policy. The release does not state a project cost.

The Xe-100 at Seadrift

The Xe-100 is a high-temperature gas-cooled reactor rated at 80 MWe and 200 MWt. It runs on TRISO-X coated particle fuel, which X-energy’s fuel subsidiary is developing. At Seadrift, four units would supply electricity and high-temperature steam to Dow’s manufacturing site and replace aging energy and steam assets there. The release says the four reactors are expected to provide power for 60 years.

The NRC found that the Xe-100 can be safely sited and built within an operating industrial site. X-energy projects a 400-meter emergency planning zone for the design, against the 10 miles typical for conventional light-water reactors. The release presents the smaller zone as what allows a reactor to sit within an operating industrial site.

The release also says X-energy has more than a dozen NRC-approved topical reports for the design. Its ARDP award is, per the release, intended to be increased to $2.15 billion in total.

X-energy’s Project Pipeline

X-energy puts its commercial pipeline at more than 11 GW, equal to 144 Xe-100 reactors. Seadrift is the first of those projects to reach a construction permit. The company listed Amazon-backed deployments with Energy Northwest in Washington and with American Electric Power in Indiana, and a partnership with Centrica targeting approximately 6 GW in the United Kingdom.

Project Partner Location Proposed Capacity Status (November 2026)
UCC Seadrift Operations Dow, DOE ARDP Texas Four units (320 MWe) NRC construction permit approved November 9, 2026
Cascade Advanced Energy Facility Energy Northwest, Amazon Washington About 320 MW first phase, up to 960 MW Announced October 2024
Sullivan County project AEP, Amazon Indiana 12 units (960 MW) Joint development agreement signed October 19, 2026
UK partnership Centrica United Kingdom Targeting approximately 6 GW Joint development agreement announced September 2025

X-energy listed on Nasdaq in April 2026. GSR’s IPO preview covers the company’s offering and business model.

References

  1. X-energy, Inc., “Dow, X-energy Proposed SMR Project Receives Historic Construction Permit for Nuclear-Powered Industrial Site,” Press Release, November 9, 2026.
  2. US Nuclear Regulatory Commission, “Long Mott Energy, LLC Construction Permit Application,” Project Page, accessed November 10, 2026.
  3. US Department of Energy, Office of Nuclear Energy, “Advanced Reactor Demonstration Projects,” Program Page, accessed November 10, 2026.
  4. Amazon, “Amazon signs agreements for innovative nuclear energy projects to address growing energy demands,” Company Announcement, October 16, 2024.
  5. X-Energy, Inc., “X-energy, Amazon, American Electric Power Partner to Bring SMR Project to Indiana,” Press Release, October 19, 2026.