Labor Cost Inflation Lifts Thacker Pass Budget 31% to $3.83 Billion

Crystallizer vessel delivered by truck to the Thacker Pass lithium project construction site in Humboldt County, Nevada

The first crystallizer from Great Basin Industries arrives at the Thacker Pass site. Photo Credit: Lithium Americas Corp

Key Points

  • On November 11, 2026, Lithium Americas raised its capital cost estimate for Thacker Pass Phase 1 to $3.83 billion, including contingency, from $2.93 billion, an increase of about 31%.
  • Labor drives most of the $895 million increase: about $395 million from craft install rates and wages, and $250 million from engineering and contractor staffing and pay.
  • The company puts the total incremental funding need at about $995 million. It expects to meet it with $650 million of joint venture contributions and, as needed, $315 million from DOE loan reserve accounts, alongside a roughly $30 million cut in the reserve requirement, per its November 11, 2026 release.
  • As of its November 11, 2026 update, the company targets mechanical completion in late 2027 and ramp-up to commercial production in 2028; procurement was over 90% complete at September 30, 2026.

Browse our Lithium Stocks List for a comprehensive overview of publicly traded lithium companies.

What Drove the $895 Million Increase

Lithium Americas Corp (NYSE: LAC, TSX: LAC) disclosed a definitive capital cost estimate for Phase 1 of its Thacker Pass project in Humboldt County, Nevada, on November 11, 2026. The estimate of $3.83 billion, including contingency, replaces a prior figure of $2.93 billion. Phase 1 is designed for nominal production of 40,000 tonnes per year of battery-quality lithium carbonate.

The company said the revision reflects advanced construction, completed detailed engineering and largely completed procurement, along with external factors that arose after its final investment decision in April 2025. Labor is the largest component. Install rates for piping, steel and equipment added about $245 million once early installation quantities showed actual productivity, and union craft wage rates and incentives added about $150 million. The company attributes both to regional competition for skilled union labor above what it had assumed.

Cost Driver Approximate Impact
Labor install rates (piping, steel, equipment) $245 million
Craft labor wage rates and compensation $150 million
EPCM and contractor staff wage rates $150 million
Additional contingency $150 million
Tariffs and logistics $100 million
EPCM and contractor staffing levels $100 million
Total increase (from $2.93 billion to $3.83 billion) $895 million

Source: Lithium Americas, Thacker Pass project update, November 11, 2026.

Bechtel, the project’s engineering, procurement and construction management (EPCM) contractor, and its subcontractors needed more engineers and construction staff than planned, and paid more to retain them. Tariff exposure is now estimated at about $60 million, down from a previously disclosed range of $80 million to $100 million, because most equipment and materials have been received. The balance of the $100 million tariff and logistics line reflects higher fuel prices, limited U.S. fabrication capacity and shipments rerouted to protect the schedule. The added contingency applies 10% to capital costs not yet committed or spent.

How the Increase Will Be Funded

The company estimates the total incremental funding requirement at about $995 million. Beyond the $895 million of capital, that figure includes a $58 million net increase in the Sustaining Capex Reserve Account required under the DOE loan through March 2028, and a $42 million net increase across other pre-completion items. The latter is partly offset by higher estimated operating cash flow during the 2028 ramp-up, which the company attributes mainly to a revised lithium carbonate price forecast.

A third omnibus waiver, consent and amendment (OWCA 3) to the DOE loan was signed on November 10, 2026, alongside agreements among the DOE, Lithium Americas and General Motors Holdings LLC. Under these, the company expects to meet the requirement with $650 million of its own contributions at the Thacker Pass joint venture level and, as needed, $315 million already credited to reserve accounts under the DOE loan. The amendments also lower the Sustaining Capex Reserve Account requirement by about $30 million during and after ramp-up.

Thacker Pass is owned by a joint venture between Lithium Americas and GM. The company said its contributions will increase its ownership percentage in the joint venture, and that it is working with the DOE and GM to finalize the effect on joint venture interests.

Construction Status at September 30, 2026

Detailed engineering is complete and procurement was over 90% complete as of September 30, 2026. More than 80% of third-party contract value had been committed and over 50% incurred. About 1,900 personnel were on site, including more than 1,600 craft workers, and the company expects, as of November 11, 2026, that to reach about 2,200 by the end of 2026 as the project reaches peak labor.

All major structural steel was on site by the end of August 2026. At the end of October 2026, 80% of the fabricated piping required was in transit or delivered. Long-lead items already received include the 115 kV main transformer and the steam turbine generator, and the company said on November 11, 2026 that it expects the remaining key long-lead equipment to arrive during November 2026.

Mechanical Completion

The construction milestone at which a plant’s equipment, piping and electrical systems are installed and checked against design, before commissioning with process materials. Production ramp-up follows, as output rises toward nameplate capacity.

The company said that with earthworks and geotechnical work behind it, the primary remaining risks include attracting and retaining craft labor, according to the November 11, 2026 release. Construction of the transload terminal west of Winnemucca, which will handle reagent deliveries, is targeted, as of November 11, 2026, for completion in 2027 to align with startup.

Spending and Liquidity

Phase 1 construction costs included in the estimate totaled $2,261.3 million cumulative to September 30, 2026, of which $1,398.7 million was incurred in the first nine months of 2026. These figures are preliminary; Lithium Americas scheduled its full Q3 2026 results for November 12, 2026.

Cash and restricted cash totaled about $1.3 billion at September 30, 2026, including $359.5 million held at the joint venture. The company received a fourth DOE loan advance of $239.0 million on August 21, 2026, bringing cumulative advances to $1.448 billion, and issued $150 million of subordinated convertible debentures to Yorkville on August 13, 2026. As of the November 11, 2026 update, $175.7 million of capacity remained under its March 2026 at-the-market equity program.