Published: November 17, 2026 | Category: Clean Energy – Geothermal
Google Signs 50 MW Superhot Geothermal PPA With Quaise Energy
Newberry Caldera in Central Oregon, with Paulina Lake, East Lake and the Big Obsidian Flow, in a 1985 archive photograph. Not an image of the Quaise project. Photo Credit: USGS/Lyn Topinka
Key Points
- Google has signed a 50 MW power purchase agreement with Quaise Energy for superhot geothermal power from Project Obsidian in Central Oregon, with deliveries starting as early as 2030.
- The power is intended to support Google’s existing data center operations in The Dalles, Oregon, where the company runs three campuses.
- Quaise’s first phase uses conventional drilling to reach superhot conditions; a second phase would be the first commercial use of millimeter wave drilling.
- Quaise closed a $180 million Series B in August 2026, including $35 million from Nabors Industries.
- Quaise expects 200 to 400 construction jobs and more than 50 permanent roles at the project.
The Terms of the Agreement
Quaise Energy, a private developer of superhot geothermal power, said on November 17 that Google had signed a power purchase agreement for 50 MW from Project Obsidian, its flagship project in Central Oregon. Quaise describes it as a step toward commercial superhot geothermal development.
Google is due to begin buying power as early as 2030. The electricity is intended to support Google’s existing data center operations in The Dalles, Oregon, and the surrounding region. The release does not state a contract term, a price or a delivery structure.
Quaise Chief Executive Carlos Araque said the agreement means the company is building the commercial foundation for superhot geothermal. He also said it helps cement the United States as the global leader in geothermal power.
Lucia Tian, Google’s Head of Advanced Energy Technologies, said the collaboration will help fuel local economic growth and support a more robust and affordable energy future for Oregon.
Power Purchase Agreement (PPA)
A long-term contract under which a buyer agrees to purchase electricity from a specific generation project at agreed terms. Developers use PPAs with creditworthy buyers to support project financing before construction starts.
Superhot Rock and Millimeter Wave Drilling
Quaise says conventional geothermal is limited to regions with hot water reservoirs, which rarely exceed 600°F. Its approach targets superhot conditions, which it says can deliver up to 10 times more clean power per well than traditional geothermal. The 10x figure is Quaise’s claim and has not been demonstrated at commercial scale.
The project is planned in two phases. The first uses conventional drilling technology to reach superhot conditions at commercial scale. The second is described as the first use of millimeter wave drilling, a technique Quaise developed after more than a decade of research at MIT.
Quaise says millimeter wave drilling can plug into existing drilling rigs. That would let the company use equipment already in the field instead of building a new rig fleet.
Millimeter Wave Drilling
A drilling method that uses high-frequency electromagnetic energy to vaporize rock instead of grinding it mechanically. Quaise says the approach is meant to reach the greater depths and temperatures where superhot geothermal resources sit, which conventional drill bits struggle to reach economically.
Google’s Oregon Footprint
Google has operated in Oregon since 2006, when it opened its first owned-and-operated data center in The Dalles. It now runs three data center campuses there, a Google Cloud region in Oregon and a Portland office. Quaise cites Google as having invested more than $7 billion in the state over 20 years.
According to the release, Google pays for 100% of the power its data centers use, and its three Oregon campuses have reached 83% carbon-free energy. Residents in the Northern Wasco County PUD service territory pay the third-lowest energy rates in the state, the release says. Google has also been Wasco County’s largest taxpayer in recent years.
The agreement adds to a wider clean energy portfolio. From 2010 to 2025, Google signed more than 240 agreements for nearly 35 GW of new clean energy, including more than 29 GW across 148 projects in North America, Quaise reports.
Google separately signed a 396 MW enhanced geothermal agreement with Fervo Energy in September 2026, at Cape Station in Utah.
Project Obsidian and Quaise’s Funding
Quaise says Project Obsidian is expected to create 200 to 400 construction jobs and more than 50 permanent engineering and operations roles. It also lists grid upgrades for reliability and royalties from electricity sales for the region as local benefits.
The company closed a $180 million Series B in August 2026. That round included a $35 million investment from Nabors Industries (NYSE: NBR), the listed drilling contractor. Quaise says technology proven at Obsidian should lower costs for future superhot projects in the United States.
Quaise is a technology developer and project developer, not an independent power producer with operating plants. Its revenue case rests on projects such as Obsidian reaching commercial operation.
What Still Has to Go Right
Deliveries are due to start as early as 2030, so the contract is a commitment to buy power from a plant that has not been built. Quaise’s own release carries a standard forward-looking statements disclaimer, saying actual results may differ materially from those described.
The first phase depends on conventional drilling reaching superhot conditions at commercial scale, which Quaise has yet to show. Millimeter wave drilling, the technology that distinguishes the company, is not planned for use until the second phase and has no commercial track record.
The release gives no price, contract length or capacity beyond the initial 50 MW. Those terms will determine how much of Obsidian’s cost the agreement supports.